Scope of Work Part A
Installation of transformer, switchboards HB1 and HB2, service and feeder conduits, wire, and concrete pads.
Coordination with PSE.
All services, materials, and labor required for functional addition of the added service installation per project plans and specifications.
Installation of generators, automatic transfers witches, conduits, wire, protective bollards, and concrete pads.
Generator and automatic transfer switch Testing and setup.
All services, materials and work needed for function addition of generators.
Part A work is funded through the Washington State Department of Transportation (Grant Number: PTS0745) Scope of Work Part B Installation of owner-furnished power blocks 3 and 4, installation of owner furnished Power Links 3A, 3B, 4A, and 4B, conduits, wire, testing, and all other items involving the functional installation of Charge Point equipment for islands 3 and 4.
Installation of owner furnished power blocks 5 and 6, installation of owner furnished Power Links 5A, 5B, 6A, and 6B, conduits, wire, testing, and all other items involving the functional installation of Charge Point equipment for islands 5 and 6.
Part B work is federally funded (Grant Number: Not assigned yet).
*CURRENT WTA VENDORS OR PAST BIDDERS: You may already have an account established in this system. Email procurement@ridewta.com before creating a new vendor account.
This Software and all data is the property of WTA and is public record pursuant to RCW 42.56. Questions about the software can be directed to procurement@ridewta.com
All actions performed in this system will be logged for auditing purposes.